Originally proposed in the 1990s, parkway development was halted during the recession. Design was made more difficult in later years when Reedy Creek Swamp was reclaimed as a mitigation bank. To adhere to the new environmental requirements, we designed a 6,200-foot reinforced concrete bridge over the mitigation bank with a specially designed arc that allows sunlight to reach ecosystems underneath the superstructure. We advocated for the use of low-pressure, segmented barges during construction and carefully monitored silt barriers to minimally impact the fragile environment.
Client/Owner
Osceola County Expressway Authority
Mileage
10 miles
Cost
$68.8 million
Services
- Engineering
- Environmental